2016-10-17 In Brief: require: Non-rising stem valve $327.00 Post Indicator (Wall or Free-standing) $551.00 Mueller It will take me a week if I get pricing to you by Monday and the Approval returned Blue Stakes will take a min of 2 days; permitting 4-days, asphalt work and trenching Will put it at least a week out. It is possible to put down a concrete pour leaving a five-foot by five-foot un-concreted square, where the 6” riser comes up through the floor. All trenching and pipe-work has to remain uncovered for inspection. The thrust block must remain uncovered for inspection Flush test and water running clear must be observed by AHJ before Riser installed on IBR flange Bacteria test also required. Riser area has to be minimum of one-foot away from any wall. Ending at the water service entrance termination flange inside the building and above the floor by site utilities contractor or Div-31 Underground. Tap Fees to be paid for by utilities contractor