FD Office: 801 264-2780 13-R MURRAY ADAPTIVE REUSE APARTMENTS 404 E 5600 S Murray UT 84107 Motel in middle of Residential area. Converting to Condos 37326 SF 4" Diam riser. Dry riser with separate FDC $5,000 (per Vineyard) 1961 Chapparrel Head to change out. 575 heads Recessed white Use new heads 14 heads on AF System in garage. 500 heads relocated 50 heads new (closets storage) 100 hrs 2hrs a head 2 guys 100 hr of demo. 750 relocate heads (1.5 hr per head) is this 60 days? Standpipe 40 hrs 3-storey Corings x4 In External Sub section AHJ Wants Dry standpipe in stair well Fire Engineering inspected. Riser alarm check valve. Cannot see all disconnects. Need to walk it, or put water on it. 2 guys 8hrs old riser in middle of building. Pull it out. (DEMOLISH) Porte Cochere disconnected. Testing 2 days 2 men beginning Existing System Analysis (added ONE day to the Labour section ) and FINAL pump up In Finals section $75 per hour 1066 hrs. 533 per fitter. add 5000 hr for misc. Travel, Staging PM. $1000 permit Design Dwg $6000 (30 days Kent) Field measure: 1066 hrs (13 weeks) 3rd Party $384 Scott Adams truck $1000 Finish B4 May-2021 Start at top floor & work down. start within 30 days of 2020-09-25 Fabrication of 50 heads T nipple RC and head 1" pipe 10 ft per unit, 50 units. $120,000 per Kent. add Kent time add for supervisory & travel. 30% profit